The Former GM Plant – Moraine, OH
Selective Demolition
General Project Scope:
HOMRICH was contracted to perform the interior demolition of the 2-story, 2,650,000 square foot structure. HOMRICH utilized 6 – 8 machines equipped with shears.
- Excavators with shear attachments were employed for removal of the auto assembly lines throughout the plant.
- Burners and man lifts were utilized for removing ceiling-mounted assembly line throughout the entire plant.
- All scrap was processed on-site for transportation to the steel mills.
- HOMRICH was responsible for the utility disconnects and securing a safe work environment. HOMRICH devised and presented a submittal plan for future manufacturing applications.