General Project Scope:

HOMRICH was contracted to perform the abatement and demolition of the 400,000 square foot high school and selective demolition of a 100,000 square foot section of the school to remain. Project highlights include:

  • LEED recycling goals were met on this project.
  • Over 10,000 tons of scrap and demolition debris was processed for recycling off-site.
  • An additional 35,000 tons of concrete and hardfill were recycled.
  • 20,000 tons of backfill was imported and placed.

The project started in June 2015 and finished on schedule in March of 2016 with no recordable injuries or near misses.