Building #116 – Akron, OH
Total Demolition | Abatement
General Project Scope:
HOMRICH was contracted to perform demolition of the large building formerly used as a Manufacturing Facility. This 6-story 1,050,000 square foot facility was abated, demolished, recycled, and restored by HOMRICH. All scrap was prepared on the project site and delivered to local steel mills. All concrete slab and footings were demolished and crushed for reuse as fill on the project site.
Soil erosion and sedimentation control permits as well as storm water permits were obtained for this project.